SCN
Construction Period
 


35 Year Life CycleROH                                                                                               

 

----------|----------|-----------|-----------|-----------|----------|----------|-----------|----------|----------|----------|----------------------à

 

                                         1             2            3               4           5             6           7           8           9 

 

                                                                                A                                                   B

 

 

 

 

 

Conventional

Entraco

Number of Pieces

7-8

3-4

Vessel Labor

1.5

X

Average Performance

60-62 dB

57-59 dB

Loss per Year

8-10 dB

+  1.4 dB

Useful Life

2-3 Years

15-17 Years

Avg. Cost per Assembly

$480

$390

Total Ownership Cost

(Outside SCN)

Material Cost Only

$2.6M/Ship

Approx. $100K/Ship

New Construction Cost

Material Cost Only

$288K/Ship

$234K/Ship